WDM11Topic 1.42 questions
Activity networks, early and late times, critical paths, float, Gantt charts and scheduling.
Specification points for this topic are coming soon.
Get a plain-language explanation, a worked example and the usual mistake.
Sign in to get a plain-language explanation of any specification point.
Original practice questions written in the style of the exam.
A project consists of the activities in the precedence table. Durations are in days.
| Activity | Duration | Immediately preceded by |
|---|---|---|
| A | 4 | – |
| B | 6 | – |
| C | 3 | A |
| D | 5 | A |
| E | 7 | B, C |
| F | 4 | B, C |
| G | 6 | D, E |
| H | 3 | F |
| I | 2 | D |
(a) Find the earliest start time and latest finish time of each activity.
(b) State the critical path and the minimum project duration.
(c) Find the total float on activities and .
(d) Calculate a lower bound for the number of workers needed to complete the project in the minimum time.